transcribe

Ep. 018 - Stop Saying Half of 2026 US Datacenter Capacity Is Canceled (Datacenter, Energy)

SemiAnalysis Weekly · 50m · transcribed Jul 2026
More from SemiAnalysis Weekly
𝕏 Share ▶ YouTube 📥 PDF 🤖 .md

Section Insights

# 0:00

Introduction to Data Center Capacity Discussion

What is the current narrative around US data center capacity?

The discussion begins with a clarification of the misleading narrative that half of the US data center capacity is canceled. The team aims to dissect the origins of this claim and provide a clearer picture of the actual situation.

  • Media reports suggest half of US data center capacity is canceled, originating from a Bloomberg headline.
  • The actual report indicates only 5 out of 12 gigawatts of planned capacity are under construction.
  • The team seeks to clarify misconceptions and present the reality of data center developments.
# 10:05

Challenges in Gas Supply for Data Centers

What are the challenges in supplying gas to data centers?

The discussion highlights significant challenges in establishing gas supply infrastructure for data centers, particularly in areas like New Mexico. Local opposition and regulatory processes hinder the development of necessary pipelines, making alternative gas delivery methods like CNG and LNG impractical.

  • Regulatory processes for gas supply lack precedent and are unlikely to be expedited.
  • Local opposition complicates the establishment of gas pipeline infrastructure.
  • Alternative gas delivery methods face logistical challenges and are not viable at scale.
# 20:11

Timeline for Data Center Power Generation

What is the timeline for data center power generation projects?

The timeline for data center projects varies significantly based on the type of agreements signed. The discussion outlines the stages from signing a deal to construction and operational readiness, emphasizing that timelines can extend beyond initial projections.

  • Timelines for data center projects depend on the nature of the agreements signed.
  • Turnkey leases and power purchase agreements (PPAs) have different implications for project timelines.
  • Completion of large-scale sites may extend to 2029 or 2030, depending on various factors.
# 30:17

Estimating Construction Timelines

How are construction timelines estimated for data centers?

The team discusses their methodology for estimating construction timelines, which includes analyzing public filings and other data sources. They emphasize the importance of understanding the different types of agreements and their impact on project timelines.

  • Estimating timelines involves analyzing public filings and various agreements.
  • Different types of agreements can significantly affect the construction timeline.
  • Understanding the nuances of each project is crucial for accurate forecasting.
# 40:23

Impact of Power Costs on Data Center Projects

How do power costs affect data center construction and operations?

The discussion reveals that while power costs are a factor, they are becoming less significant relative to overall project costs. The increasing revenue per megawatt in the cloud sector allows for greater flexibility in managing power expenses.

  • Power costs are becoming less relevant as revenue per megawatt increases.
  • Solutions like Bloom energy are not prohibitively expensive compared to overall project costs.
  • Labor rates and material costs are complicating construction estimates, favoring faster deployment solutions.

Transcript

0:04 Hello everyone. Welcome back to semi analysis weekly. I'm here this week with the data center energy and industrials team. that's Jeremy, Ellie, and Rake. We're going to talk about a couple of articles they put out recently. The first is stop saying half of 2026 US data center capacity is canceled. Nice title. We'll clarify some stuff there. And the second one >> pretty descriptive. Yeah. The second one is about behind the meter data center power generation 40 gawatts by 2028.

0:36 Guys, welcome to the show. >> Thank you Jordan. Yeah, thanks for having us. >> We're covering three continents on this one. We got a break in Singapore. >> The latency >> we'll try. >> I never s analysis, bro. >> Normal day. Yeah. Okay. So, let's let's dig in. the the first article had a great title and obviously the conclusion didn't bury the lead at all. but I've been seeing this all over the media where everybody keeps saying that half of data center capacity is canceled. You guys walk through maybe reasons why people are saying this and then clarified some stuff as to like what's actually happening. can you give a lay of the land as to what's reality, what's fake?

1:28 Yeah. I can start with the why. the there I think Bloomberg started this right with this big headline of like half of US data center capacities delayed. Everyone else started piling in and citing the same number and you know that most of these articles point to the same underlying source right which is a report that's available out there. And you know when you look at the reports the report says it was 12 gawatt of data center capacity scheduled to go online in the US in 2026 and only five is under construction right and I think you know for us when we saw this we're like why why is everyone talking about this like just it's just not possible and and you know I think the funny thing is that like you don't even need to like do anything fancy you can just disprove this data so easily like I I don't know man. Amazon announced publicly they built 4 gawatt in 2025.

2:29 Is that going up or not in 2026? Obviously it's going up. Amazon alone is probably going to add like you know 5 gawatt plus so that's basically all they think is going to be going live like one company. you know obviously got all the hypers skaters. Coreweave coreweave you know is going to add a gigawatt in 2026. All of that is under construction. So you're telling me core weave one gig under construction is like you know a fifth of the market like come on there's a massive issue in the denominator you're just wrong just don't publish that. So yeah that's a high level if you want to add more deeds but for me I think that's the that was the trigger is just looking at the underlying source you're like oh guys you're just off it's just wrong.

3:17 Yeah, we had seen this getting like paraded around quite a bit and you know, I mean like everybody would go viral just kind of reposting it. I was like, "My god, this is this is mind-numbing to see every time on my Twitter timeline." and obviously like our clients are pretty smart. Our clients are going to take every like data source they can and compare them against each other. So, we also had to help every client on that front. And it was like, well, why don't we just write a newsletter about this and say like, "Yo, this this is just really fake. we don't have to really go into this as much anymore. Please just read the newsletter. a lot of the kind of baseline here is not worth really talking about sometimes.

3:56 yeah. So, that's why we that's why we ended up writing it. Yeah. And in addition to that, like it's not even like the spirit of the article was fake in a sense. Like you can imagine or you can forgive somebody getting the exact numbers wrong. But if I look at this chart that you guys put out around how the outlook that you guys have forecasted from roughly the the last year like April of last year to May of this year, it hasn't even changed by 5%. I'll put this chart up on screen. So maybe you can talk through a little bit about like what the reality of some of these forecasts are, which is that some stuff gets, you know, delayed, but there's very few cancellations that are actually showing up in the market, right?

4:48 >> Well, I would disagree. I think there's a pretty substantial amount of cancellations. just what we keep saying is that these cancellations are are early stage projects, right? I'm not sure if you have this one on the screen but like there's this map of the US where we show like the large load requests right which is like slightly different but kind of goes to the same point as of today you have over a terowatt of data center load that is requested by operators in the US alone right this chart is as of six months ago it more than doubled now so we have over a terowatt obviously you know the whole US system right now peak load 750 gawatt you're not you know double it right now in sort of you know just a couple years it's just not possible it's not a reality so obviously this is fake there's a lot of early stage projects and it makes sense essentially you know I think the data center market started booming towards the end of 2023 that's when early folks started to realize hey there's going to be a big constraint on this the first big deal started to get signed at that moment and you know since then there's been like this massive search for power and that means that you know everyone was trying to find where is where is power available and that leads to some behaviors where because everyone is doing it then if you want to be successful you also yourself have to be aggressive plan multiple options and this is that is actually nothing new like hyperskers have always had multiple options when evalu evaluating projects it's even more critical in times of constraint and so you would see sometimes for one final investment decision see hyperskers maybe have 10 different options right and so that would be 10 projects where they're sort of talked to the local counties you know they they they talk to like the utilities and so on and so forth.

6:29 and these are not all realistic and they're sort of just testing the field and be like okay which county can enable me to build my large scale project where do I have the workforce or do I have the supply chains you know where do I where can I build it? So anyways, there's an over supply of very early stage projects and you know our point and that was sort of Rake's brilliant phrasing the cloudcoded projects is that I just loved it. This is amazing. is that as AI is I guess not very good at filtering, right? So when you have humans in the loop, yes, it's pretty obvious that some of these announcements are way too aggressive. We gave a bunch of examples in the article of you know folks where you know they announce 10 gawatt project this they say the first trench of 500 meg is going to be available next year and then you click on the website you see contact us nothing more and then you start digging into whatever permits and whatnot you see nothing so at some point you're just like okay these people probably have a lot of land in Texas or something like that but they don't yet have a real project right any human judgment would sort of filter that but I guess for AI Okay, it's still pretty hot these days. so if you want to build a forecast of the industry, you have to base it on realistic forecasts, you know, or semi analysis, extensive trade regulation has always been our playbook.

7:48 Not just data centers, but also chips because obviously this has downstream implications on Nvidia upstream on the AI labs, their revenue, all of that stuff connects to each other. That's you know the semi- analysis flywheel covering every single one of these industries and building a a cohesive cohesive view. you know others don't do that and easily you know, struggle to find the ability to quit the size outputs. >> Makes sense. So, in the article, you guys cover three different types of data center delays. One, the aggressive announcement by a newer data center developer. Two, an advanced project with overly optimistic construction timelines that might just be a delay or pushed out or something.

8:29 And then the third one is really something facing permitting and local opposition issues. So Ellie, can you come in here and maybe explain one of those examples where we do look in and find something in permits? >> Yeah. Yeah, sure. So, the the the project which which is facing quite a lot of push back locally not yeah not just New Mexico local opposition but also from from jurisdictional and reg regulatory kind of characters. is a project Jupit or Oracle's project Jupiter in New Mexico. So yeah, essentially they're trying to construct a a pipeline to feed the the behind the meter data center in in in Da Da Anna province. and essentially the the this pipeline hasn't been built. and the route that they that they are planning to that they want to build on is is hasn't been approved. They haven't got a pro route. They have got a secondary approved route. and essentially the they the whole all of the ways to kind of get gas to the site don't seem very feasible.

9:48 >> So looking at there's a pipeline issue which they're trying to make make happen. But there seem every every FK filing that I see that comes through on the docket, they haven't they haven't made much progress or any of progress at all because essentially it's defaulted to a type of regulatory process which essentially there is no precedent for it being done sooner than essentially two years. And given the local opposition as well, that there's it's very unlikely that it'll be sped up. there are other options to getting gas to a site like you could ship truck CNG and LNG to to a facility as as we point out.

10:34 However, this at scale you know getting to that's I think the only proven like delivery of CNG at scale is kind of around 200 megawatt or like max 200 megawatt. I think maybe even that's optimistic and there aren't many there aren't many manu there aren't many producers in the local area and there are not not enough trucks to to facilitate that. So essentially yeah there's not only a pipeline which doesn't exist and has no viable route of existing but getting gas to the site via CNG and LNG is even harder is is just not not viable. So yeah, no it's it just I think it br it like it it's it demonstrates kind of an interesting bottleneck which could occur with more behind the meter facilities is like building gas pipeline infrastructure especially in territories like New Mexico that's quite not not not extremely it's not extremely friendly area towards that that kind of infrastructure.

11:39 Yeah, I would that that's how we we basically look through the filings. We look through all of the filings. You know, we look we we already had it on our radar because they had issues with the initial turbines that they were trying to use at the site. So, they ended up switching to Bloom fuel cells. and through through kind of that that research, I I spotted this this timeline and I was just like this is this doesn't make sense. Why are there so many local all the all these all this push back all these all these local comments and then yeah just FK and the other regulators are still thinking about it.

12:17 >> So is this an example of a clawcoded data center project? >> So I I I think what this speaks to is rather that there's like we have to re rethink the way we build data centers in order to meet this demand. But it's it's not like other people had built one gigawatt sites before this, right? Like we're still in the early in the evenings of bringing the first gigawatt scale data centers to market. so we had we had to try a whole lot of different things. No one has experience doing this. maybe today yes but like as of you know one year ago, two years ago, no one had experience. So obviously you know the you try all these new thing there's going to be errors. so that that's why you know the way we analyze big projects like this we always try to think of what is a reasonable timeline.

13:02 I think it's pretty you know it's pretty common in the industry that you have folks that pitch more aggressive timelines but I think it happens and and that's valid for you know every single industry not data centers contractors I think anyone that has a construction we tell you they tend to be always over optimistic suppliers are always over optimistic it's not like this is anything new and especially when you try something much bigger at that scale with new designs and so on and so forth in new new locations new counties you know new municipalities handling it then obviously you're going to face a few challenges. so that's a great fit for a category of projects that are already well advanced because they already got financing. They got a release from Oracle OpenAI booked sorry Oracle charted to OpenAI. So there's already a massive contract on this but facing execution challenges now.

13:52 >> Yeah, makes sense. Maybe we could talk about behind the meter now. So you guys in the the second article published some some numbers on this first y-axis on one of your charts in a little while there Jeremy which is pretty cool. So when we talk about the size and scale of some of these projects I guess the behind the meter net additions when compared to like the available grid capacity is a significant difference. and you specifically forecasted over 40 gawatts of net additions of data center capacity behind the meter by 2028.

14:36 that number is effectively like it rails to zero right now, right? Like there's a few behind the meter projects, but people are just getting going ordering turbines. The supply chain's ramping up. What does it actually take to get there? Do you do you expect that behind the meter projects are more at risk of cancellation based on some of the reasons Ellie just described or less at risk of cancellation because they don't depend on the grid? >> Excellent question man excellent question. so I guess the first thing is okay this this this forecast sort of depicts our analysis mostly of the US grid right and looking at looking at the gap context we're not adding enough generation on the grid to meet that demand that is going to you know be in the tens of gawatts per year and just keeps increasing every single year based on all of the signals that we keep seeing right so now is it realistic to assume there's going to be 40 gawatts of new behind the meter data centers added by 2028.

15:40 You know, you have to look at what is being planned right now. you know, I can tell you in the last two weeks, 3 gawatts of data center deals were signed for behind the meter purposes, right? So, deals are happening. site selection, I think, happened beforehand. I think you saw a massive move in part of 24, mostly 25 where folks really starting started to have like access to a gas pipeline as one of the main site selection criteria. I think you started seeing sort of diversions where where maybe some of the traditional data center operators were more focused on let's be in a tier one market like Northern Virginia you know let's find grid connected sites because we need the five nights and you saw sort of more newer operators maybe more you know AI fields that sort of tried to foresee this trend I think Cruso is a great example you know they've been quite ahead of the curve on this and they've been able to you know sign massive deals in you know like Abene 600 172 gig megawatt with Microsoft announced publicly like Crusoe in Q1 that you know that's behind a meter for example. so anyways I I think we're getting there in terms of is the supply ready for it because there's like many many developers that have secured sites.

16:50 in terms of manufacturers I think I can probably do an extremely detailed rundown. in terms of probability of delays, I I I think the probability of delays is lower with behind a meter because of the the way these grid constraints play out is that as a developer, you know, you talk to utility they have no binding obligation to abide by the schedule that they provided you. And what keeps happening time and time again is you know with the anecdotes we hear from developers. Hey, I thought I was going to get 500 megawws by you know 2027. I had a handshake with the utility or whatever. And then you know a couple months later they tell me actually sorry bro I can't do it. it's going to be you know 100 by 2028. you're 500 by 2032 because I got to do bigger network upgrades because hey actually I didn't consider my analysis. Other guy also wants it. you don't have enough generation coming and so on and so forth. and so yeah, I think utilities are sort of realizing they'll face with more delays than they thought. and so in many cases if your strategy is only grid, you're extremely likely to be disappointed. if anything that's more so on the on the power side behind the meter, I guess adds a new risk which is more the ex execution layer like can you build a power plant on time? Can you get the permitting that adds a new set of complexities? We're going to see some high-profile delays. obviously the New Mexico one based on our analysis is the highest of profiles, right?

18:21 Basically a hundred billion dollar deal for OpenAI with Oracle. so the highest type of you know delays that you can have. hope that hope they're going to solve it on time. You know, wish them the best. I think you're going to see more of that, but I think in terms of raw volumes because there's like so many options now for developers, you're going to see a lot of success stories as well. And you know, Colossus one, sorry, Colossus one and two are proof that you can do this at scale.

18:44 Well, I don't know if they're the best examples because of the issues they have with regards to permitting, but they're demonstrating like it can be done and there's other doing it. Crusoe is another example. >> I was just going to add to that like we're seeing the OEMs really reacting to the behind the meter story as well. So, you know, we're seeing obviously the ma, you know, the major OEMs, the established players like, you know, your Seammens, G, you know, all all those guys expanding manufacturing capacity. But then throughout the stack, you're seeing new new players, new entrance, new new types of technology, and then recycled all types of technology which we've written about in several different notes. But yeah, I think that that's that's a really like increasing that that's a good tell for like you know how this market and is is developing at the speed and and also I think on on the permitting thing that's that's something which could delay since we've seen you know companies switch to bloom fuel cells in order to kind of get speed to well possibly speed to power because of manufacturing footprint of of bloom fuel cells but also it's lower NOx and socks and emissions. So yeah, so they yeah and I think that was the Nubius New Jersey facility for example is they switched to Bloom I think it was Bergen Bergen turbines prior. So yeah in order to yeah to combat the permitting issues there. So we might see, you know, shifting around of technology. maybe relocating to more to other states like to Texas rather than in on the East Coast. but yeah, know that's that would be kind of the the story going on in the BTM market right now. Full full broke.

20:28 >> Makes sense. Yeah. Jeremy, maybe we can go back to one thing you said related to the like size of some of this. So at this point when you say that you signed you you know about 3 gawatt signed in the last week and we're talking about in the in the context of the article 40 gawatt of behind a meter power generation by 2028.

20:59 Can you just high level for the general audience that listens to this podcast, describe a rough timeline for when something gets signed versus when construction starts versus when you can power the first trunch of GPUs on versus when a large site like a g gawatt scale site might actually be completed? Is 3 gawatt signed in mid 2026 actually going to have anything by 2028? Is it a 2029 2030 story? Like is this a year and a half, 2 and 1/2 years, three, four, five?

21:33 >> Yeah, I would say it varies a lot depending on what what signed actually what actually is signed. there there's a bunch of deals out there. the bulk of the volumes these days would be turnkey leases where let's say a company like I don't know digital realy QTS builds a data center for Microsoft you know they sign up for lease turnkey lease where sort of QTS takes on everything and Microsoft just rents you have power shells which are a bit different which is sort of a lower lower bound on the developer and sort of more capex from the tenant. you have just power deals, right? So it's basically a PPA let's say Oracle with Volta grid and in the Czech 4 county Texas site essentially a PPA there's no data center involved right so depending on the deals the timelines can vary rule of thumb would be say deal sign 18 month you have capacity but you have the first ranch and then depending on how fast you sort of can build it but I think it's pretty clear that these days the expectation is that the ramp from sort of first capacity first phase to full ramp is expected to be you know faster and faster and the point we make in that article is that from a buyer's perspective, behind the meter is now becoming much more attractive than grid because you're in control of your destiny, right? Like, hey, you know, you're going to have gigawatts by x amount of time. Now, obviously, it has to be permitted and so on and so forth, but at least from a power standpoint, you know exactly what you're going to have on site and when, provided that there's, you know, delays from the suppliers and so on and so forth. so the idea is, hey, if you have all of this power, then you also need to build a data center because otherwise useless, right? so the expectation is that is that that that the ramping up this 3 gawatt is not going to take 5 years. is going to be much faster than this, right? And generally what you observe on the marketplace is that when there's a gigawatt scale deal being signed, let's say you know Oracle with stack in New Mexico with Vantage in Texas, you see that financing for the whole project takes place >> shortly after, right? We saw like, you know, Digital Bridge money for Vantage just maybe a month after after the lease was signed. We're talking about, you know, $25 billion of financing. So the whole the money is already secured, right? Once you have that deal, you secure all the money and then you just try to build as fast as possible. it's not going to take five years. It's going to be much trouble than that.

23:51 >> Yeah. So not one, not five, somewhere in between. Makes sense. >> Buy the model. >> Buy the model. Indeed. Yeah. Everybody listening, buy the model. Okay. Okay, I want to show you guys one chart and and get your reaction here because I thought this one was fascinating in terms of understanding the market share. I think a lot of the people who buy the model are using the data that you guys provide in order to make decisions for companies on the legend here. AWS and orange, Google and blue, Meta in this fuchsia pink color let's call it, and then Microsoft and green. So these these are the hyperscalers. They make up a large percentage of the market in terms of how many megawatts they have under construction.

24:40 the market share that these guys represent going forward is I don't know just really interesting as we see them kind of compete with each other. So, I don't know, Rake, what's your take on the relationship between the hyperscalers competing each with each other and then maybe hyperscalers versus everyone else in the market in terms of just how big everybody's going right now in terms of competing with each other? Well, I mean, I think when we take a look at kind of the capacity race, you're going to notice that it's mostly driven by the a the respective AI labs.

25:19 So, most of the time like an AWS capacity build out will be kind of fueled by anthropic, right? Or meta will typically be for MSL. Microsoft typically open AI as well. We know that there's some anthropic deals going on there as well, but by the model. in any case, these are going to be in any case, these are going to be yeah, like the the drivers of the data center buildout right now, right? Because they're the ones who have the capital able to actually build out the data center capacity that's needed for the AI labs. They're the ones who have the kind of investment grade back like investment grade financing able to start these projects and get them going forward.

26:01 most projects struggle with, you know, yeah, actually getting the financing. Like if you're a Neocloud, which if you're listening to this later on, maybe you already have read the other article. but if you're a NeoCloud, it's a bit hard to get the financing to start and go ahead and like get a data center and go ahead and buy the GPUs and expend the capital for all of this like build out, right? Because it's going to come out to probably billions of dollars. so in essence you're mainly left with hyperscalers driving the AI buildout or it's going to be very very wellunded or well capitalized neoclouds like if we look at any of the kind of Blackstone backed guys any of the KKRbacked guys they've got plenty of money coming in from them to support their own buildout but in any case I forgot your second question actually so if you could say that again.

26:55 >> No problem. Yeah. Yeah, it is interesting. Maybe let me ask a different one because I'm thinking of it now listening to you talk. So, at the very beginning of this article, we were commenting on the public research that has driven all of these articles in the media about how half of 2026 US data center capacity is canceled. But that chart that I put on screen and roughly what you're saying about the hyperscalers building for the AI labs says that you know even if you just take two of those four hyperscalers who've got more than 5 gawatts under construction and then there's the whole rest of the market the other two hyperscalers and then everybody else. So can you opine on where the gap is in terms of people trying to do research on data center capacity under construction and just missing entire gigawatts worth of capacity. That's a real thing for next year.

27:56 >> Yeah. >> Yeah. Yeah. luckily Jeremy was able to explain the whole article in 3 minutes earlier. So I can kind of expand on what he said. It's a bit too efficient with this communication. basically when you have a model like ours, we do everything kind of in a bottoms up way, right? Where we have like each individual data center is like for example a row in an Excel file for us, right? And so you can kind of get the forecast for each individual building, the tenant. If the end user is an open AI or an anthropic you already have that information for that building in specific, then you can go ahead and find the timeline for the building. Right? A lot of people don't a lot of people don't have the expertise to judge timelines on these things.

28:41 Right? when we go ahead and do our data center research. I like to joke that Jeremy and I have probably seen probably seen over 10 to 20,000 satellite images, right? So, not a lot of people can say that they understand like what that single gray pixel on a brown floor means. It's like, oh, that's actually the concrete padding coming in. that's going to be a good sign. Hopefully, we see vertical construction, which is the darker gray pixel in the corner over there that most people wouldn't get. so the satellite images are super useful for us, but like that's just one that's really fun to talk about. the other stuff is a bit more boring, which is where we go through every kind of permit portal for every county, city, state, country in the world, right? we like to talk about how much we use Claude as you see in the article, 170K in a week. the cloud part, everybody loves the cloud part. Anyway, so we got, you know, our lovely chart on the kind of front of the page where it's, hey, $170,000 spent in a week, right? We're we're token maxing, you know, we're token mogging, meta or whatever you want to call it.

29:50 more tokens per employee than, you know, yeah, Meta is one of the But in any case, we tend to use Claude and we've actually built out basically an entire harness and workflow for our agents. We love our agents that go ahead and scan and scrape every permit portal basically around the world down to state, municipality, and city and county level. And with this, we get a ton of public filing information that allows us to basically estimate timelines with that. And without going to too much more detail, that's one part of basically three in our methodology. And for the other three, you can also buy the model to figure that out.

30:34 and so I put the put the cloud code spend chart on screen here. So we've got >> to be clear to describe this, >> the color coding is a per user breakdown, I believe. >> Yes. >> And people who are looking can see the really big yellow block at the bottom. >> Yeah. Yeah. >> 90% sure. >> The culprit may be on this. The culprit is on the phone right now. Yeah. That's Jeremy just abs just melting anthropics GPUs at the bottom there.

31:08 >> Yeah. Yeah. Yeah. The ones that he's looking at from the sky are also cooking up some of his requests there. Yeah. >> Yeah. Exactly. They saw they saw Jeremy spend and they went and bought out the SpaceX capacity right after. So, thanks to him. Good forecast. >> >> Yeah, we're we're moving markets now like that. Go ahead, Ellie. What you thinking about over there? >> No, I was just gonna yeah, make a joke about Jere Jeremy's usage and making a profit good with Pope. that was Yeah. No. yeah. So interest Yeah, it's going to be interesting to see how much of these Yeah. how much is going to be built behind the meter from from the the main AI labs as well. yeah see yeah saying and I think also the kind of vary you know behind the meter is there's one that's one term there are kind of various different kind of definitions of kind of moving energy that moving kind of energy on site not taking all of it from the grid I mean you can colllocate your energy can have a net metering kind of solution which is yeah more of a kind of interactive interactive relationship with the grid you can have fully islanded off-grid you know energy energy supply for your data center. But yeah, I think that's a that's going to be the kind of thing that that that is going to be interesting to observe in the future as the more of them are built.

32:47 seeing what's preferred I mean which state fully islanded bitter grid connection maybe that might hedge some you know interconnection in the future. Also then there's a you know what happens to these assets these turbines once you know once maybe they do connect to the grid they might end up being part of the grid themselves. So like a lot of these turbines could be uses peers gas peers and help solve help with solving the actual like lack of power on the grid itself. I mean, obviously there's transmission to sort out, but yeah, there so I think it's a it's a it's it's more symbiotic than than than it's kind of portrayed by a lot of other outlets. I think it's more of it's not I don't think it's one or the other. It will be Well, I don't think it'll be one or the other forever.

33:35 >> Makes sense. Yeah. Well, let me throw this chart on screen that I thought was really awesome from the second article about behind the meter power generation, kind of based on what you're talking about. this here's a breakdown of the supply ceiling by OEM per year. So we can see that increase as some of these suppliers that would be responsible for the power generation in behind the meter gas settings and how much capacity they're increasing in terms of how much they can produce. And I mean two things jump to mind when I look at this. First of all is just how much it's increasing.

34:08 So it seems to be going up at roughly the rate at which we're going to increase the power generation requirement. that's a good thing. And then the second thing is just how many different suppliers there are available. We look at stuff that's a constraint in the market. Whether this is like GPUs or wafers or memory or anything else rough generally speaking when something's a constraint it depends on like one two three suppliers but when you have this diversity where the top eight that are on screen and colorcoded make up just more than half let's say but then your footnote at the bottom of this chart shows like 25 more names that can possibly produce power. I mean, we've about this previously, but maybe you guys can walk through like just how diverse the options are available for power generation is and and what sort of shared supply chain there is that benefits people who are looking for alternatives when they need power and they're not sure where to get it for behind the meter.

35:20 >> Yeah, sure. So I mean there as I I was saying like there would be kind of established players who have like a large supply chain where you know and they've been in the business for years and years and years. they have manufacturing capacity globally. they have quite they you know they're they're quite they quite often say in earnings that you know the bottlenecks are kind of the castings the bottlenecks are the the blades for whatever kind of turbine or aero derivative or resip kind of whatever solution they're they're they're offering but it it seems it seems that like this is not slowing anything down because they're still announcing capacity increases and they're still and they're still saying that these capacity increases are driven by AI AI demand growth. So it it seems to be actually a little bit of a narrative talking about the constraints to castings and you know kind of upstream constraints to to building building these turbines. is a bit of a narrative from last year. I think this year it's now the the large OEMs are sort of like realizing that actually more many more players are coming to the market and they're trying to keep their market share not and not lose it.

36:29 I think that that literally that was in a seaman's pre-close call this morning or yesterday. So they're very much kind of aware of this growing market and that you know they can't kind of play the scarcity game and try and get everyone to to freak out because people did not freak out but people saw an opportunity and are converting you know old old parts of you know plane technology into kind of into engines and then and then you know boiler boilers and obviously there's a kind of there's the autoderative kind of options as well. So that's we're seeing all of these different types come into the into the market. Some with kind of more the that have more of an advantage in terms of permitting and some some less. I think there's also something which we I've I've been noticing is more of the yeah more of a car industry kind of having a larger play in in in larger playing a larger role in the data center industry in the sense that like EVs are not are not as I mean they're quite popular in California and the east coast but like in lots of the US there's kind of EV growth has been quite slow and so a lot of that manufacturing capacity I think is is going towards well we have the Tesla as a good good one and then we saw and then Ford as well providing best so battery storage battery energy sort of storage solutions to the data center industry as well so we're seeing we're seeing kind of these existing players switch to the data center industry as well so yeah I hope that answers your question but >> yeah it's cool yeah makes sense Jeremy what's jumping of mind here when you're hearing us talk about all the different suppliers that you can use for biometer power generation.

38:27 >> Yeah. I mean like I think it was always to be expected. last year the narrative was behind a mirror is not possible because there's this free manufacturers that are so slow and you know everyone was sort of throwing that chart the famous chart of like you know how much gas orders there were in like the early 2000s where you had this massive sort of you know wave and everyone was saying GEV and Seammens are so scarred of this era because they invested massively in capacity and so they're going to be very conservative right but you know the that that leaves a market opportunity and one one question would like to ask management teams at these power companies is you know how AI pill are you essentially you know how much do you believe how much risk are you willing to take there's also a function of how easy is it for you to take risk in the sense that you know what's your economics on building more capacity near factories and there's a bunch of companies that you know score very well the one that we've been flagging for a while we especially doubled down like at the end of 25 when we did our big deep dive is blue energy because you know I think clearly the management team is very AIP I think they have economics that sort of enable them to build capacity faster than others and the the the behind the mirror conversation is is really interesting because the like I I think it's like you know company by company they're sort of adjusting their mindsets as they adapt to the new reality and also sort of solution by solution you keep adjusting your expectation just based on constraint so what I'm saying is that initially everyone was like okay this is going to be bridge power it's going to be matter of like one two years I run off up offg grid and then I'm going to have my you know my grid come in and maybe it's going to be backup and so you you would only consider like systems that are good at backup but that's the ultimate disadvantage for something like bloom is that you know it's like not very good at backup you has to be run extremely hot it's 15,000 degrees C takes like two days as far as I know to go from zero to 100 so for backup it's you know really not the system. But hey, if you have no other alternative, then may you know, maybe it's that maybe you just have to to go for it, right?

40:36 Like if your if your option is your other option is I'm not going to have power, then you know, you're screwed. You're not going to be competitive in the marketplace. and you know, other issues are like power costs. And I think when you look at the the recent like SpaceX deals, I think it's pretty clear that sort of the revenue per megawatt that folks are making on the cloud side also on the lab side on the model side like revenue per me go up at every layer I guess and as that increases it means that power costs are increasingly irrelevant. and power costs for solutions like Bloom are not that expensive anyways. with regards to you know what we have in Europe for example with the grid.

41:16 >> well certainly not as a as a percentage of the total construction costs of the project or when you consider the GPUs and stuff. People can pay double for the turbines they want compared to >> I don't know somebody else that's competing in the market for them and not really affect the total capex of train. And the other thing is like also estimating the bit of materials I think has proven quite complicated for many of these vendors especially as labor rates are going to the moon and you thought you were going to have local labor but hey actually everyone in Texas is you know already occupied building data center so you have to call people from Denver or from Ohio and obviously it's much more expensive and this means that this also favors solutions that are fast to install first fast to deploy because your B is sort of more predictable your time are more predictable and both on the labor side and on the sort of full deployment side. So you know I think again like analyzing timelines and ease of deployment is key and I think Tom solutions score extremely well and I also think we're going to keep seeing more and more new entrance because you know everyone looks for capacity earlier and the standards are sort of dropping right the the there's a few new companies that entered recently that are basically coming from the automotive industry not themselves like their source engines from the automotive industry. And then when you think of this you're like wow automotive like you know we're talking about like 100 gawatt plus per year of production and that's an industry everyone knows runs at very low utilization rates you know 50% 40% these factories are not doing too well.

42:50 so the capacity and the incentive that these guys have to sell their engines through the data center market is also tremendously high. So you know that unlocks gigantic capacity. >> Absolutely. At a minimum it's diversification for their business. So the the one thing that we haven't talked about necessarily yet is alternatives to gas let's say I'm sure a lot of people who are new to this space who are listening are thinking in their mind about you know what about renewables what about solar wind hydro nuclear like you know who's considering that what's going on so I'll throw two charts on the screen and then hopefully you guys can comment just on the reality of being able to use renewables plus batteries or you know any renewables let's say.

43:40 So >> yeah. >> yeah, go for it. >> So yeah, this is grid connected. so the the point of this obviously like name plate additions are overall growing and we're talking about you know 60 gawatt 50 gawatt per year. So it's a lot but as everyone knows you know the 100 me gawatt of solar is not a true gawatt for the grid because you know it's intermittent and only turns on at certain hours and so on and so forth right pretty simple. So you know depends on the areas you see an ELCC value. So adjusted for the actual capacity value it brings to the grid. depending on the area it can be like 10% of it, 20% of it, sometimes below 10, sometimes over 20. Depends on you know it's all sort of very complex system level calculation. the problem is again like the grid is also sort of facing all of the transmission issues. It's intrinsically slow. There's giant interconnection cues. So I think the question the real question for solar and batteries is can you do it behind the meter? Like you know can people build these things on site? I I I think it's going to happen. and we're gonna have much more content on that published on our website. So stay tuned.

44:45 obviously the high level challenge is that the the land required to build like massive amount of solar is just tremendous. so logistically these projects are fairly complex. You know if you're talking about I need 20,000 acres just to throw solar panels at it. it's going to be for a gigawatt data center or something like that then you know buying all that land can get complicated. sometimes what happens you know during the course of this sort of land buyout is that the land holder sort of realize hey this guy wants to build you know hundred billion dollar project maybe I'm going to sell my land 10x is more expensive than what he thought I was going to get right so that sort of stuff happens as well so anyways the complexity of building these massive projects fairly elevated which removes the time to power angle to some extent for solar and batteries but as folks sort of get bigger and bigger and start planning you know multiple years ahead. I think there there's already a lot of big projects like this underway.

45:43 and the other issues obviously SMRs and nuclear you know no you know I'm not going to reinvent the wheel. This is slow stuff right. everyone knows building nukes takes time. so again not a time to power. So right now you have a lot of non-binding LOIs in the market or non-binding deals that are contingent contingent on like milestones and execution and getting the regulatory approvals and so on and so forth. I think in the 2030s we're going to see a gigantic diversification of energy sources to power data centers. I think for the 2020s we're going to be very much in the gas world.

46:17 >> Makes sense. Okay. As we move to wrap here guys, what's Yeah. Anything left unsaid? Ellie, what you got? I was just I was just going to say that we might see kind of as in moving on more kind of carbon I'm start to see more kind of carbon capture utilization storage facilities being kind of colloccated with BTM sites and with data centers as well. I think that's something interesting to observe as well going forward >> to know. Yeah. Rick, how about you?

46:49 What's jumping a mind man? you know, I don't know if I have too much here. I think, I think we covered that the listener needs to know. I'm not going to lie. No, I don't know. I think, yeah, I think the BTM movement is going to be very, very big. But I think I think maybe Jeremy touched on it already, but it's interesting to see the like what we call kind of like peak turbine in 2026 where it's like there was a huge overby or like a huge overpurching of turbines in 26 where not everybody knew what to do with them. Not everybody could figure out how to get the permits or not everybody could figure out how to build the data center to actually use the turbines. And so you ended up seeing a lot of these turbines go kind of underutilized or I mean later on start to hit the secondary market for example. But I think this is going to read pretty bearish to people at first and people might kind of freak out on it. But long term we're still very very probe behind the meter. I just think it'll be interesting to watch how people interpret this though because it's going to it'll probably keep picking up, right? Like you'll probably see your favorite projects turbines start to hit the market at some point and you're going to freak out and then the question is is it over, right? So, we don't think it's over. we still quite like BTM, but I think that's going to be a fun dynamic to watch play out.

48:25 >> Okay, we got to end going around the horn here. Rick, what what's your favorite project? project. >> My favorite project you Oh, actually I might have one. I might have one. I I would go the NScale Norway project. I love this one. Actually love this one. This one. >> Jeremy, what's your favorite project or or top three? You You don't have to choose. >> Colossus 2, bro. Colossus 2. Fast, efficient, scale, super high revenue. W All, >> what's yours?

48:58 I I would say Venevius switch and new see Si right >> why not quite >> Oracle New Mexico all right go ahead >> I know I don't know Oracle New Mexico >> that's a lovely we spent the most time with that one I think yeah >> yeah where are we going to get robots building data centers >> we need robots we need robots building data centers They're coming. They're coming. Hey, we should you guys should watch the other podcast. You should watch the other podcast. We talk about this.

49:36 >> I don't even think we did. >> What year are you going to see a data center fully built by robots? >> Fully built by robots. Wow. Oh, that's a lot of manhour. >> Electricians. >> Lot of man hours. What is that like eight and a half million manh hours? dude, >> lot of man. maybe 2029 at the earliest 20 2030 2030 >> breaks going to back calculate actuator constraints in the supply chain >> let me let me think about how many permanent magnets are being manufactured right now that's a tough one that's a tough one man yeah the lord pull oh man all right thanks for joining good All right.

50:24 >> Cheers. Bye. Bye, Dylan.

Summary

The podcast discusses recent articles on data center capacity and power generation, clarifying misconceptions about cancellations and exploring the future of behind-the-meter (BTM) data center power generation. The team emphasizes that while there are delays in some projects, the overall demand and capacity growth remain strong, particularly driven by hyperscalers in the AI sector.

- Misleading headlines about half of US data center capacity being canceled stem from misinterpretation of reports; actual construction is ongoing.
- Many projects are in early stages and face delays, but cancellations are often exaggerated and do not reflect the overall market.
- Behind-the-meter power generation is forecasted to add over 40 gigawatts by 2028, driven by demand from AI labs and new operational strategies.
- The diversity of suppliers for power generation is increasing, with many new entrants from various industries, including automotive.
- Challenges remain for renewable energy integration, particularly regarding land acquisition and permitting for large-scale solar projects.
- The podcast highlights the importance of accurate forecasting and understanding the complexities of data center construction timelines.
- The BTM movement is expected to grow significantly, despite potential short-term market fluctuations due to over-purchasing of turbines.

Questions Answered

What is the current narrative around US data center capacity?

The discussion begins with a clarification of the misleading narrative that half of the US data center capacity is canceled. The team aims to dissect the origins of this claim and provide a clearer picture of the actual situation.

What are the challenges in supplying gas to data centers?

The discussion highlights significant challenges in establishing gas supply infrastructure for data centers, particularly in areas like New Mexico. Local opposition and regulatory processes hinder the development of necessary pipelines, making alternative gas delivery methods like CNG and LNG impractical.

What is the timeline for data center power generation projects?

The timeline for data center projects varies significantly based on the type of agreements signed. The discussion outlines the stages from signing a deal to construction and operational readiness, emphasizing that timelines can extend beyond initial projections.

How are construction timelines estimated for data centers?

The team discusses their methodology for estimating construction timelines, which includes analyzing public filings and other data sources. They emphasize the importance of understanding the different types of agreements and their impact on project timelines.

How do power costs affect data center construction and operations?

The discussion reveals that while power costs are a factor, they are becoming less significant relative to overall project costs. The increasing revenue per megawatt in the cloud sector allows for greater flexibility in managing power expenses.